[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},885539,572,1,"单选题","某建设项目污水拟排入附近一河流，地表水环境影响评价等级为三级。根据《环境影响评价技术导则—地表水》，该项目水环境现状水质的调查时期至少应包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","枯水期",true,{"key":16,"text":17,"correct":18},"B","平水期",false,{"key":20,"text":21,"correct":18},"C","平水期和枯水期",{"key":23,"text":24,"correct":18},"D","丰水期、平水期和枯水期","各类水域在不同评价等级时的水质调查时期可见表。题干中该项目地表水环境影响评价等级为三级，查表可知该项目水环境现状水质的调查时期至少应包括枯水期。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]