[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},885536,572,1,"单选题","某拟建项目对河口的环境影响评价工作级别定为一级，一般情况下该河口水质调查时期应为一个潮汐年的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","丰水期和平水期",false,{"key":16,"text":17,"correct":14},"B","平水期和枯水期",{"key":19,"text":20,"correct":14},"C","丰水期和枯水期",{"key":22,"text":23,"correct":24},"D","丰水期、平水期和枯水期",true,"水环境现状调查的时期与水期（潮期）的划分相对应。河流、河口、湖泊与水库一般按丰水期、平水期、枯水期划分；海湾按大潮期和小潮期划。一级评价最为严格，丰水期、平水期、枯水期这三个阶段都要调查。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]