[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},885528,572,1,"单选题","此建设项目（上题）污水水质复杂程度为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","简单",false,{"key":16,"text":17,"correct":14},"B","复杂",{"key":19,"text":20,"correct":21},"C","中等",true,{"key":23,"text":24,"correct":14},"D","不复杂","污水水质的复杂程度按污水中拟预测的污染物类型以及某类污染物中水质参数的多少划分为复杂、中等和简单三类：①复杂，污染物类型数≥3，或者只含有两类污染物，但需预测其浓度的水质参数数目≥10；②中等，污染物类型数＝2，且需预测其浓度的水质参数数目＜10；或者只含有1类污染物，但需预测其浓度的水质参数数目≥7；③简单，污染物类型数＝1，需预测浓度的水质参数数目＜7。由上题可知，建设项目排放了两类污染物，且需监测的水质项目为9个，符合中等水质的条件。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]