[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},885358,572,1,"单选题","根据《建设项目环境影响评价技术导则—总纲》，环境现状调查与评价内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","区域污染源调查",false,{"key":16,"text":17,"correct":14},"B","环境保护目标调查",{"key":19,"text":20,"correct":21},"C","社会环境现状调查与评价",true,{"key":23,"text":24,"correct":14},"D","自然环境现状调查与评价","根据《建设项目环境影响评价技术导则—总纲》（HJ 2.1—2016）的规定，环境现状调查与评价内容包括：①自然环境现状调查与评价；②环境保护目标调查；③环境质量现状调查与评价；④区域污染源调查。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]