[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},885350,572,1,"单选题","（2018年）根据《建设项目环境影响评价技术导则总纲》，建设项目环境保护措施的可行性验证内容不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","拟采取措施的长期稳定运行和达标排放的可靠性",false,{"key":16,"text":17,"correct":14},"B","拟采取措施的技术可行性和经济合理性",{"key":19,"text":20,"correct":14},"C","生态保护和恢复效果的可达性",{"key":22,"text":23,"correct":24},"D","拟采取措施的清洁生产水平",true,"明确提出建设项目建设阶段、生产运行阶段和服务期满后（可根据项目情况选择）拟采取的具体污染防治、生态保护、环境风险防范等环境保护措施；分析论证拟采取措施的技术可行性、经济合理性、长期稳定运行和达标排放的可靠性、满足环境质量改善和排污许可要求的可行性、生态保护和恢复效果的可达性。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]