[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885336":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},885336,572,1,"单选题","进行环境影响经济损益分析应从建设项目产生的正负两方面环境影响，以（ ）的方式，估算建设项目所引起环境影响的经济价值，并将其纳入建设项目的费用—效益分析中，作为判断建设项目环境可行性的依据之一。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","定性",false,{"key":16,"text":17,"correct":14},"B","定量",{"key":19,"text":20,"correct":21},"C","定性与定量结合",true,{"key":23,"text":24,"correct":14},"D","定性与半定量结合","以建设项目实施后的环境影响预测与环境质量现状进行比较，从环境影响的正负两方面，以定性与定量相结合的方式，对建设项目的环境影响后果（包括直接和间接影响、不利和有利影响）进行货币化经济损益核算，估算建设项目环境影响的经济价值。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]