[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},885215,571,1,"单选题","污水处理厂二沉池主要用于生化处理系统的泥水分离和回流污泥浓缩，保证出水水质，采用表面负荷设计二沉池表面积时，计算流量应该取：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","污水处理厂的最大时设计流量加污泥回流量",false,{"key":16,"text":17,"correct":14},"B","污水处理厂的最大时设计流量加污泥回流量和污泥排放量",{"key":19,"text":20,"correct":21},"C","污水处理厂的最大时设计流量",true,{"key":23,"text":24,"correct":14},"D","污水处理厂的最大时设计流量加混合液内回流量","提示 二沉池的沉淀面积以最大时流量作为设计流量，不考虑回流污泥量；但二沉池的某些部位则需要包括回流污泥的流量在内，如进水管(渠)道、中心管等。",{"id":6,"name":27,"category":28,"favorite":29},"注册环保工程师 - 专业基础","建筑工程",0]