[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},885178,571,1,"单选题","生活垃圾焚烧厂日处理能力达到什么水平时，宜设置3条以上生产线？",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","大于300t\u002Fd",false,{"key":16,"text":17,"correct":14},"B","大于600t\u002Fd",{"key":19,"text":20,"correct":14},"C","大于900t\u002Fd",{"key":22,"text":23,"correct":24},"D","大于1200t\u002Fd",true,"提示 记忆题。建设规模分类与生产线数量见题16-3-3解表。",{"id":6,"name":27,"category":28,"favorite":29},"注册环保工程师 - 专业基础","建筑工程",0]