[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-881765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},881765,569,1,"单选题","一般性建筑屋面雨水重力流排水系统与溢流设施的“设计重现期”应取不小于( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1～3年",false,{"key":16,"text":17,"correct":14},"B","2～5年",{"key":19,"text":20,"correct":21},"C","10年",true,{"key":23,"text":24,"correct":14},"D","50年","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（暖通空调专业）","建筑工程",0]