[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-881071":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},881071,569,1,"单选题","关于电子工业洁净室性能测试，下列哪一项是不正确的？",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6级洁净室空气洁净度等级的认证测试的最长时间间隔为1年",false,{"key":16,"text":17,"correct":18},"B","温度、相对湿度检测，应在净化空调系统至少稳定运转12h后进行",true,{"key":20,"text":21,"correct":14},"C","对于单向流洁净室风量和风速测试，其测点数不应少于5点",{"key":23,"text":24,"correct":14},"D","洁净度检测，每一采样点最小采样时间为1min","根据《洁净厂房设计规范》GB500711附录C表C2.1，选项A正确。根据第C1.3条，选项B错误，没有规定稳定运行时间。根据第C3.1条，选项C正确。根据第C3.1条，选项D正确。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（暖通空调专业）","建筑工程",0]