[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-880718":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},880718,569,2,"多选题","下列关于空调系统调试的说法中，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由建设单位总负责，施工单位负责操作、设计单位负责技术指导、监理单位负责监督检查",false,{"key":16,"text":17,"correct":18},"B","空调系统带冷(热)源的正常联合试运行不应少于8h",true,{"key":20,"text":21,"correct":18},"C","风机和水泵连续运转不少于2h",{"key":23,"text":24,"correct":18},"D","冷水机组连续运转不少于8h","BCD","",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（暖通空调专业）","建筑工程",0]