[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-880048":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},880048,569,1,"单选题","北方某厂的厂区采用低压蒸汽采暖，设有凝结水回收管网。一新建1000㎡车间设计为暖风机热风采暖，系统调试时，发现暖风机供暖能力严重不足。但设计的暖风机选型均满足负荷计算和相关规范规定。下列分析的原因中，哪一项不会导致该问题发生？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","蒸汽干管或凝结水于管严重堵塞",false,{"key":16,"text":17,"correct":14},"B","热力人口低压蒸汽的供气量严重不足",{"key":19,"text":20,"correct":21},"C","每个暖风机环路的疏水回路总管上设置了疏水器，未在每一台暖风机的凝结水支管上设置疏水器",true,{"key":23,"text":24,"correct":14},"D","车间的凝结水总管的凝结水压力低于连接厂区凝结水管网处的凝结水压力","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（暖通空调专业）","建筑工程",0]