[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},879936,569,1,"单选题","建筑节能分部工程验收与单位工程竣工验收的顺序，正确的应是下列哪一项？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建筑节能分部工程验收应在单位工程竣工验收合格后进行",false,{"key":16,"text":17,"correct":14},"B","单位工程竣工验收应与建筑节能分部工程验收同时进行",{"key":19,"text":20,"correct":21},"C","单位工程竣工验收应在建筑节能分部工程验收合格后进行",true,{"key":23,"text":24,"correct":14},"D","建筑节能分部工程验收与单位工程竣工验收的顺序由验收单位商定","《建筑节能工程验收规范》GB504117第1.0.5条。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（暖通空调专业）","建筑工程",0]