[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879767":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},879767,568,2,"多选题","关于污泥输送，下列说法哪几项正确？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初沉污泥可用隔膜泵输送",true,{"key":16,"text":17,"correct":18},"B","压力输泥管最小转弯半径为管径的4倍",false,{"key":20,"text":21,"correct":14},"C","重力输泥管最小设计坡度为1%",{"key":23,"text":24,"correct":18},"D","皮带输送机倾角应小于30°","AC","根据《室外排水设计规范》7.5.4条，管道输送污泥，弯头的转弯半径不应小于5倍管径。根据《室外排水设计规范》7.5.2条，皮带输送机输送污泥，其倾角应小于20°。故B、D错误。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（给排水）","建筑工程",0]