[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879744":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},879744,568,2,"多选题","下列污水厂厂址选择及总体布置的设计做法，哪些是正确的？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","污水厂建设按远期规划、分期征地方式",true,{"key":16,"text":17,"correct":18},"B","综合办公楼位于厂内夏季主导风向的下风向",false,{"key":20,"text":21,"correct":18},"C","污泥处理区位于厂内冬季主导风向的上风向",{"key":23,"text":24,"correct":14},"D","地下污水厂供电系统按一级负荷设计","AD","根据《室外排水设计规范》6.1.5条，生产管理建筑物和生活设施宜集中布置，其位置和朝向应力求合理，并应与处理构筑物保持一定距离。办公室、化验室和食堂等的位置，应处于夏季主导风向的上风侧，朝向东南。污泥处理区位于厂内常年主导风向的下风向。故B、C错误。根据《室外排水设计规范》6.1.19条，污水厂的供电系统，应按二级负荷设计，重要的污水厂宜按一级负荷设计。故D正确。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（给排水）","建筑工程",0]