[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879741":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":21},879741,568,2,"多选题","某工厂废水六价铬浓度为80mg\u002FL，拟采用还原法处理，下列关于该废水处理工艺设计和运行控制条件的说法中，哪几项正确？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","第一步：控制pH值为2，先投加硫酸亚铁将六价铬还原成三价铬",true,{"key":16,"text":17,"correct":18},"B","第一步：控制pH值为9，先投加硫酸亚铁将六价铬还原成三价铬",false,{"key":20,"text":21,"correct":14},"C","",{"key":23,"text":21,"correct":18},"D","AC",{"id":6,"name":26,"category":27,"favorite":28},"专业知识（给排水）","建筑工程",0]