[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879556":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},879556,568,2,"多选题","以下有关机械循环集中热水供应系统管网计算的叙述中，哪几项是错误的？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定时热水供应系统的循环流量应按供水时段内循环管网中的水循环2～4次计算",true,{"key":16,"text":17,"correct":18},"B","居住小区集中热水供应系统室外热水干管设计流量的计算，与居住小区室外给水管道设计流量的计算方法相同",false,{"key":20,"text":21,"correct":18},"C","计算导流型容积式水加热器循环水泵扬程时，可不计加热器的水头损失",{"key":23,"text":24,"correct":14},"D","选择循环水泵时，其水泵壳体承受的工作压力应以水泵扬程确定","AD","A项见《建筑给水排水设计规范》5.5.6条：“定时热水供应系统的热水循环流量可按循环管网中的水每小时循环2次～4次计算”。循环的目的是保证非高峰供水时段内系统内必要的水温。B项见《建筑给水排水设计规范》5.5.1条。C项见《建筑给水排水设计规范》5.5.10-2条的注解。D项见《建筑给水排水设计规范》5.5.10-3条。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（给排水）","建筑工程",0]