[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879384":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},879384,568,2,"多选题","在城市给水系统设计流量的确定和计算时，关于管网漏损水量计入与否，下述说法正确的是哪几项？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","二级泵站的设计流量，应另外计入管网漏损水量",false,{"key":16,"text":17,"correct":18},"B","一级泵站的设计流量，应另外计入原水输水管(渠)的漏损水量",true,{"key":20,"text":21,"correct":14},"C","从二级泵站向管网输水的管道的设计流量，应另外计入管网漏损水量",{"key":23,"text":24,"correct":18},"D","从一级泵站向净水厂输水的原水输水管(渠)的设计流量，应另外计入原水输水管(渠)的漏损水量","BD","",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（给排水）","建筑工程",0]