[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879349":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},879349,568,2,"多选题","下列关于在河流取水构筑物的表述，哪几项正确？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","取水构筑物处的水深一般要求不小于2.5m",true,{"key":16,"text":17,"correct":18},"B","取水构筑物应设置在桥梁前或桥梁后1km以外的地方",false,{"key":20,"text":21,"correct":18},"C","取水构筑物淹没进水孔上缘距设计最低水位深度最小取0.5m",{"key":23,"text":24,"correct":14},"D","取水构筑物顶面进水孔下缘距河床的高度不得小于1.0m","AD","取水构筑物应避开桥前水流滞缓段和桥后冲刷、落淤段。取水构筑物一般设在桥前0.5～1.0km或桥后1.0km以外的地方。依据《室外给水设计规范》5.3.12条，取水构筑物淹没进水孔上缘在设计最低水位下的深度，应根据河流的水文、冰情和漂浮物等因素通过水力计算确定，当①顶面进水时，不得小于0.5m；②侧面进水时，不得小于0.3m；③虹吸进水时，不宜小于1.0m，当水体封冻时，可减至0.5m。故B、C错误。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（给排水）","建筑工程",0]