[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879340":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},879340,568,2,"多选题","为解决某城镇的生活给水管网供水量有时不能满足城镇用水量的要求，采取下列哪几项措施是可行的？( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从邻近有足够富余供水量的城镇生活给水管网接管引水",true,{"key":16,"text":17,"correct":14},"B","新建或扩建水厂",{"key":19,"text":20,"correct":21},"C","从本城镇有自备水源的某工厂的内部供水管网接管引水",false,{"key":23,"text":24,"correct":14},"D","要求本城的用水企业通过技术改造节约用水，减少用水量","ABD","依据《室外给水设计规范》7.1.9条，城镇生活饮用水管网，严禁与非生活饮用水管网连接；城镇生活饮用水管网，严禁与自备水源供水系统直接连接。故C错误。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（给排水）","建筑工程",0]