[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},879182,568,1,"单选题","下列关于雨水量确定与控制的设计做法，哪项错误？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在规划设计大中型城市的雨水管网系统时，应采用推理公式法计算雨水设计流量",true,{"key":16,"text":17,"correct":18},"B","当某地区的综合径流系数高于0.7时，需要建设渗透和调蓄设施",false,{"key":20,"text":21,"correct":18},"C","整体改建后的地区，同一设计重现期的暴雨径流量必须小于等于改造前的径流量",{"key":23,"text":24,"correct":18},"D","某城镇仅有15年自动雨量记录，设计暴雨强度公式采用年多个样本法编制","依据《室外排水设计规范》3.2.1条，当汇水面积超过2k㎡时，宜考虑降雨在时空分布的不均匀性和管网汇流过程，采用数学模型法计算雨水设计流量。大中型城市的汇水面积都超过2k㎡，宜采用数学模型法。故A错误。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（给排水）","建筑工程",0]