[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},879177,568,1,"单选题","分流制污水管道的设计断面应根据下列哪项流量计算确定？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平均日平均时污水流量",false,{"key":16,"text":17,"correct":14},"B","平均日最大时污水流量",{"key":19,"text":20,"correct":14},"C","最大日平均时污水流量",{"key":22,"text":23,"correct":24},"D","最大日最大时污水流量",true,"设计流量=平均日平均时生活污水流量×总变化系数+工业企业最高日最大时流量。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（给排水）","建筑工程",0]