[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},879158,568,1,"单选题","污水厂中预处理单元和二沉池的设计流量应按下列哪项确定？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平均日流量",false,{"key":16,"text":17,"correct":14},"B","平均日流量乘以日变化系数",{"key":19,"text":20,"correct":14},"C","平均日流量乘以时变化系数",{"key":22,"text":23,"correct":24},"D","平均日流量乘以总变化系数",true,"《室外排水设计规范》6.2.4条：“污水处理构筑物的设计流量，应按分期建设的情况分别计算。当污水为自流进入时，应按每期的最高日最高时设计流量计算。”",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（给排水）","建筑工程",0]