[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-879131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},879131,568,1,"单选题","以下关于污水厂沉淀池的表面负荷和适用条件中哪一项是不恰当的？( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","初沉池设计表面负荷一般大于二沉池",false,{"key":16,"text":17,"correct":14},"B","辐流式沉淀池适用于大中型污水处理厂",{"key":19,"text":20,"correct":21},"C","竖流式沉淀池适合做二沉池",true,{"key":23,"text":24,"correct":14},"D","平流式沉淀池适用于大中小型污水处理厂","竖流式沉淀池做二次沉淀池是可行的，但并非“适合做”。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（给排水）","建筑工程",0]