[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-878969":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},878969,568,1,"单选题","某全日制循环的管道直饮水系统，拟将变频调速供水泵兼做循环泵，则水泵设计流量应根据下列哪项流量确定？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","瞬时高峰流量(或设计秒流量)",true,{"key":16,"text":17,"correct":18},"B","最大小时流量",false,{"key":20,"text":21,"correct":18},"C","瞬时高峰流量+循环流量",{"key":23,"text":24,"correct":18},"D","最大小时流量+循环流量","用供水泵兼做循环泵时，回水管上设置控制流量的阀门，水泵流量按设计秒流量选取。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（给排水）","建筑工程",0]