[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-878955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},878955,568,1,"单选题","关于建筑排水设计流量计算，以下哪项正确？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","用水时段较为集中的建筑物，排水设计秒流量采用同时排水百分数法",true,{"key":16,"text":17,"correct":18},"B","公共建筑物内的大便器同时排水百分数，与同时给水百分数相同",false,{"key":20,"text":21,"correct":18},"C","公共建筑物生活排水小时变化系数，与生活给水用水小时变化系数不相同",{"key":23,"text":24,"correct":18},"D","住宅的生活排水设计秒流量，直接与当地气候条件和生活习惯有关","由《建筑给水排水设计规范》4.4.6条可知A正确。同样由4.4.6条可知，冲洗水箱大便器排水为12%，故B错误。依据《建筑给水排水设计规范》4.4.2条，公共建筑生活排水定额和小时变化系数应与公共建筑生活给水用水定额和小时变化系数相同。故C正确。由《建筑给水排水设计规范》4.4.5条可知，不同地方不应按同一公式计算，故D错误。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（给排水）","建筑工程",0]