[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-876858":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},876858,565,1,"单选题","基础建设项目的审批程序是( )。",[11,15,19],{"key":12,"text":13,"correct":14},"A","先审批环境评估报告，后审批项目设计任务书",true,{"key":16,"text":17,"correct":18},"B","先审批项目设计任务书，后审批环境评估报告",false,{"key":20,"text":21,"correct":18},"C","环境评估报告和项目设计任务书可以同时审批","根据《中华人民共和国环境保护法》第十三条，建设项目的环境影响报告书，必须对建设项目产生的污染和对环境的影响作出评价，规定防治措施，经项目、主管部门预审并依照规定的程序报环境保护行政主管部门批准。环境影响报告书经批准后，计划部门方可批准建设项目设计书。",{"id":6,"name":24,"category":25,"favorite":26},"专业基础知识（给排水）","建筑工程",0]