[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-876135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},876135,565,1,"单选题","污水泵站的设计流量一般按( )污水量确定。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平均日平均时",false,{"key":16,"text":17,"correct":14},"B","平均日最高时",{"key":19,"text":20,"correct":14},"C","最高日平均时",{"key":22,"text":23,"correct":24},"D","最高日最高时",true,"污水泵站的设计流量一般按最高日最高时污水量确定。",{"id":6,"name":27,"category":28,"favorite":29},"专业基础知识（给排水）","建筑工程",0]