[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-875816":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},875816,564,1,"单选题","某冷水系统有2台同型号的冷水机组，已知机组在100%负荷时的COP为5.7，75%负荷时的COP为6.4，50%负荷时的COP为6.7，当系统的负荷正好等于1.5倍的机组额定负荷时，方案1为2台机组均在75%负荷运行，方案2为1台机组额定负荷和1台机组50%负荷运行，方案1相对于方案2的节能率为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6%",true,{"key":16,"text":17,"correct":18},"B","8%",false,{"key":20,"text":21,"correct":18},"C","10%",{"key":23,"text":24,"correct":18},"D","12%","",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（暖通空调专业）","建筑工程",0]