[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-875742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},875742,564,1,"单选题","热力网与供暖用户采取有混水降温装置的直接连接，热网设计供回水温度为110℃\u002F70℃，用户设计供回水温度为85℃\u002F60℃，用户供暖设计热负荷为100kW，混水装置的设计流量为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2000～2100kg\u002Fh",false,{"key":16,"text":17,"correct":18},"B","2100～2200kg\u002Fh",true,{"key":20,"text":21,"correct":14},"C","2200～2300kg\u002Fh",{"key":23,"text":24,"correct":14},"D","2300～2400kg\u002Fh","",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（暖通空调专业）","建筑工程",0]