[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-875584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},875584,564,1,"单选题","某车间的内区室内空气设计计算参数为：干球温度20℃，相对湿度60%，湿负荷为零，交付运行后，发热设备减少了，实际室内空调冷负荷比设计时减少了30%，在送风量和送风状态不变(送风相对湿度为90%)的情况下，室内空气状态应是下列哪一项？(该车间所在地为标准大气压，计算时不考虑围护结构的传热)( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","16.5～17.5℃，相对湿度60%～70%",false,{"key":16,"text":17,"correct":18},"B","18.0～18.9℃，相对湿度65%～68%",true,{"key":20,"text":21,"correct":14},"C","37.5～38.5kJ\u002Fkg，含湿量为8.9～9.1g\u002Fkg",{"key":23,"text":24,"correct":14},"D","42.9～43.1kJ\u002Fkg，含湿量为7.5～8.0g\u002Fkg","",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（暖通空调专业）","建筑工程",0]