[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-875062":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},875062,563,1,"单选题","",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","33.3m",false,{"key":16,"text":17,"correct":18},"B","32.3m",true,{"key":20,"text":21,"correct":14},"C","31.0m",{"key":23,"text":24,"correct":14},"D","28.3m","按6层建筑确定的最小服务水头为28m，不失一般性，先假设H点为控制点。则E点自由水头为：28+20+3.2-24=27.2。F点自由水头为：27，2+24+0.5-25=26.7其他各点自由水头类似求得，结果为：G点27.2，C点26.8，B点30.6，D点28.4，A点31.0。此时已经看出原来假设的H点并不是真正的控制点，F，G，C点均低于28m水头，且F点最低；亦即控制点为F点，且与28m水头相差(27.0-26.7)=1.3m。将以上计算结果统一提升1.3，得：A点自由水头为32.3m，即为所求。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（给排水）","建筑工程",0]