[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-868447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},868447,559,1,"单选题","模板拆除作业之前，应确认混凝土强度已达到（ ）的要求，应对作业区进行围圈、设置明显标志或监护人员。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","模板强度",false,{"key":16,"text":17,"correct":18},"B","拆模强度",true,{"key":20,"text":21,"correct":14},"C","模具强度",{"key":23,"text":24,"correct":14},"D","模架强度","",{"id":6,"name":27,"category":28,"favorite":29},"C证（专职安全员）","建筑工程",0]