[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-867880":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},867880,558,2,"多选题","附着式脚手架应在（ ）的阶段进行检查和验收。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","首次安装完毕。",true,{"key":16,"text":17,"correct":14},"B","提升或下降前。",{"key":19,"text":20,"correct":14},"C","提升、下降到位，投入使用前。",{"key":22,"text":23,"correct":24},"D","遇有七级大风与大雨后；",false,{"key":26,"text":27,"correct":24},"E","停用超过半个月","ABC","（6）附着式升降脚手架应在下列阶段进行检查与验收：1）首次安装完毕。2）提升或下降前。3）提升、下降到位，投人使用前。（7）在附着式升降脚手架使用、提升和下降阶段，均应对防坠、防倾覆装置进行检查，合格后方可作业。（8）附着式升降脚手架、高处作业吊篮所使用的电气设施和线路应符合《施工现场临时用电安全技术规范》（JGJ46）的要求。（9）高处作业吊篮应按规定逐台逐项验收，并经空载运行试验合格后方可使用。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省C2证（土建安全员）","建筑工程",0]