[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-867864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},867864,558,2,"多选题","吊运模板时，下列说法符合规定的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","作业前应检查绳索、卡具、模板上的吊环，必须完整有效，在升降过程中应设专人指挥，统一信号，密切配合",true,{"key":16,"text":17,"correct":14},"B","吊运大块或整体模板时，竖向吊运不应少于2个吊点，水平吊运不应少于4个吊点，吊运必须使用卡环连接，并应稳起稳落，待模板就位连接牢固后，方可摘除卡环",{"key":19,"text":20,"correct":14},"C","吊运散装模板时，必须码放整齐，待捆绑牢固后方可起吊",{"key":22,"text":23,"correct":14},"D","严禁起重机在架空输电线路下面工作",{"key":25,"text":26,"correct":27},"E","遇6级及以上大风时，应停止一切吊运工作",false,"ABCD","吊运模板时，必须符合下列规定：1）作业前应检查绳索、卡具、模板上的吊环，必须完整有效，在升降过程中应设专人指挥，统一信号，密切配合。2）吊运大块或整体模板时，竖向吊运不应少于2个吊点，水平吊运不应少于4个吊点。吊运必须使用卡环连接，并应稳起稳落，待模板就位连接牢固后方可摘除卡环。3）吊运散装模板时，必须码放整齐，待捆绑牢固后方可起吊。4）严禁起重机在架空输电线路下面工作。5）5级风及其以上天气应停止一切吊运作业。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省C2证（土建安全员）","建筑工程",0]