[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-867473":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},867473,558,1,"单选题","连墙件应靠近门架的横杆设置，距门架横杆不宜大于（ ）mm。连墙件应固定在门架的立杆上。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","150",{"key":19,"text":20,"correct":21},"C","200",true,{"key":23,"text":24,"correct":14},"D","300","架体与建筑物拉结应符合下列规定：1脚手架必须采用连墙件与建筑物做到可靠连接。连墙件的设置应满足《建筑施工门式钢管脚手架安全技术规范》JGJ128相关要求；2连墙件设置的位置、数量应按专项施工方案确定，并应按确定的位置设置预埋件；3连墙件应靠近门架的横杆设置，距门架横杆不宜大于200mm。连墙件应固定在门架的立杆上；4连墙件宜水平设置，当不能水平设置时，与脚手架连接的一端，应低于与建筑结构连接的一端，连墙杆的坡度宜小于1：3。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省C2证（土建安全员）","建筑工程",0]