[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-866054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},866054,557,1,"单选题","某设备重量85t，施工现场拟采用两台自行式起重机抬吊方案进行就位，其中索吊具重量3t，自制专用抬梁重量5t，风力影响可略。制定吊装方案时，最小计算载荷为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","106.48t",false,{"key":16,"text":17,"correct":14},"B","108.90t",{"key":19,"text":20,"correct":21},"C","112.53t",true,{"key":23,"text":24,"correct":14},"D","122.76t","起重机在吊装重物运动的过程中，要产生惯性载荷，习惯上把这个惯性载荷称为动载荷。在起重工程中，以动载荷系数计入其影响。一般取动载荷系数K1为1.1。在多分支（多台起重机、多套滑轮组、多根吊索等）共同抬吊一个重物时，由于工作不同步这种现象称为不均衡。在起重工程中，以不均衡载荷系数计入其影响。一般取不均衡载荷系数K2为1.1～1.2。在起重工程的设计中，为了计入动载荷、不均衡载荷的影响，常以计算载荷作为计算依据。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省C1证（机械安全员）","建筑工程",0]