[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-865970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},865970,557,1,"单选题","当多台塔式起重机在同一施工现场交叉作业时，低位塔式起重机的起重臂端部与另一台塔式起重机的塔身之间的距离不得小于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2m",true,{"key":16,"text":17,"correct":18},"B","3m",false,{"key":20,"text":21,"correct":18},"C","4m",{"key":23,"text":24,"correct":18},"D","5m","当多台塔式起重机在同一施工现场交叉作业时，应严格控制相邻塔机间的安全距离，编制专项方案，并采取防碰撞的安全措施。任意两台塔式起重机之间的最小架设距离应符合下列规定：1）低位塔式起重机的起重臂端部与另一台塔式起重机的塔身之间的距离不得小于2m。2）高位塔式起重机的最低位置的部件（吊钩升至最高点或平衡重的最低部位）与低位塔式起重机中处于最高位置部件之间的垂直距离不得小于2m。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省C1证（机械安全员）","建筑工程",0]