[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-865337":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},865337,556,3,"判断题","项目经理必须组织做好隐蔽工程的验收工作，参加地基基础、主体结构等分部工程的验收，参加单位工程和工程竣工验收；必须在验收文件上签字，不得签署虚假文件。（）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"项目经理必须组织做好隐蔽工程的验收工作，参加地基基础、主体结构等分部工程的验收，参加单位工程和工程竣工验收；必须在验收文件上签字，不得签署虚假文件。",{"id":6,"name":21,"category":22,"favorite":23},"江苏省B证（项目负责人）","建筑工程",0]