[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864798":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864798,556,2,"多选题","建筑施工现场临时用电工程专用的电源中性点直接接地的220V、380V三相四线制低压电力系统，必须符合下列规定（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用三相供电",false,{"key":16,"text":17,"correct":18},"B","采用三级配电系统",true,{"key":20,"text":21,"correct":18},"C","采用TN-S接零保护系统",{"key":23,"text":24,"correct":18},"D","采用二级漏电保护系统",{"key":26,"text":27,"correct":14},"E","采用IT配电系统","BCD","《施工现场临时用电安全技术规范》（JGJ46）规定，施工现场临时用电工程专用的电源中性点直接接地的220\u002F380V三相四线制低压电力系统必须符合下列规定：（1）采用三级配电系统。（2）用TN-S接零保护系统。（3）采用二级漏电保护系统。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]