[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864792":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864792,556,2,"多选题","高大模板支撑系统拆除前，（）应核查混凝土同条件试块强度报告，浇筑混凝土达到拆模强度后方可拆除，并履行拆模审批签字手续。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","企业主管经理",{"key":19,"text":20,"correct":21},"C","项目技术负责人",true,{"key":23,"text":24,"correct":21},"D","项目总监",{"key":26,"text":27,"correct":14},"E","安全部长","CD","高大模板支撑系统拆除前，项目技术负责人、项目总监理工程师应当核查混凝土同条件试块强度报告，浇筑混凝土达到拆模强度后方可拆除，并履行拆模审批签字手续。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]