[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864784":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864784,556,2,"多选题","某公司承建的培训中心项目，局部层高达8.2m，为保证该处高支模体系的安全施工，项目部编制了高大模板支撑体系专项施工方案，并按规定要求对方案进行了审核，但未组织专家论证。2010年10月21日，项目经理安排了木工班组搭设该处高支模，并于3天后开始混凝土的浇筑，绕筑过程中发生坍塌事故，导致2人死亡。针对此类事故，请结合所学知识，回答以下问题： 混凝土浇筑施工方案应包括（）等内容。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","混凝土泵管的固定措施",true,{"key":16,"text":17,"correct":14},"B","混凝土浇筑方式",{"key":19,"text":20,"correct":14},"C","浇筑路径",{"key":22,"text":23,"correct":14},"D","振捣方式",{"key":25,"text":26,"correct":27},"E","浇筑人员持证上岗要求",false,"ABCD","混凝土浇筑施工方案：应对混凝土泵管采取固定措施，明确混凝土浇筑方式、浇筑路径及振捣方式。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]