[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864770":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864770,556,2,"多选题","建设行政主管部门及监督机构应将高大模板支撑系统作为建设工程安全监督重点,加强对方案（）的监督。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制方法",false,{"key":16,"text":17,"correct":18},"B","审核论证",true,{"key":20,"text":21,"correct":18},"C","验收",{"key":23,"text":24,"correct":18},"D","检查",{"key":26,"text":27,"correct":18},"E","监控程序","BCDE","建设行政主管部门及监督机构应将高大模板支撑系统作为建设工程安全监督重点，加强对方案审核论证、验收、检查、监控程序的监督。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]