[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864756":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864756,556,2,"多选题","根据模板工程管理规定，下列说法正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","模板施工中应设专人负责安全检查",true,{"key":16,"text":17,"correct":14},"B","发现问题应报告有关人员处理",{"key":19,"text":20,"correct":21},"C","发现异常时可以继续施工，但应采取相应防护措施",false,{"key":23,"text":24,"correct":14},"D","发现异常时立即停工和采取措施",{"key":26,"text":27,"correct":14},"E","修复或排除险情后，方可继续施工","ABDE","模板施工中应设专人负责安全检查，发现问题应报告有关人员处理。当遇险情时，应立即停工并采取应急措施；待修复或排除险情后，方可继续施工。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]