[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864752":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864752,556,2,"多选题","基坑围护结构施工完工后、地下结构工程施工前，必须由（）单位对基坑工程进行联合验收。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设",true,{"key":16,"text":17,"correct":14},"B","设计",{"key":19,"text":20,"correct":14},"C","施工",{"key":22,"text":23,"correct":24},"D","监测",false,{"key":26,"text":27,"correct":14},"E","监理","ABCE","基坑围护结构施工完工后、地下结构工程施工前，必须由建设、设计、施工、监理单位对基坑工程进行联合验收，对基坑开挖与支护工程的稳定性、时效性等方面出具书面意见，并报工程所在地建筑工程质量、安全监督部门备案，合格后方可进行地下结构施工。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]