[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864744":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864744,556,2,"多选题","高大模板支撑专项施工方案包括（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程概况",true,{"key":16,"text":17,"correct":14},"B","体系和方案选择",{"key":19,"text":20,"correct":14},"C","构造要求",{"key":22,"text":23,"correct":24},"D","基础承载力情况",false,{"key":26,"text":27,"correct":24},"E","水平剪刀撑设置情况","ABC","高大模板支撑专项施工方案包括工程概况、体系和方案选择、构造要求、设计验算、施工图、施工要求、混凝土浇筑施工方案、施工计划、应急救援预案、施工安全保证措施、劳动力计划。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]