[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864693":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864693,556,2,"多选题","建筑工程项目实行总承包的，专项方案应当由施工总承包单位组织编制，其中（）等专业工程实行分包的。其专项方案可由专业承包单位组织编制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","高大模板支撑工程",false,{"key":16,"text":17,"correct":18},"B","深基坑工程",true,{"key":20,"text":21,"correct":18},"C","起重机械安装拆卸工程",{"key":23,"text":24,"correct":14},"D","拆除、爆破工程",{"key":26,"text":27,"correct":18},"E","附着式升降脚手架","BCE","建筑工程实行施工总承包的，专项方案应当由施工总承包单位组织编制。其中，起重机械安装拆卸工程、深基坑工程、附着式升降脚手架等专业工程实行分包的，其专项方案可由专业承包单位组织编制。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]