[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864681":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},864681,556,2,"多选题","危险性较大的分部分项工程的含义（）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","是指建设工程施工过程中存在的",true,{"key":16,"text":17,"correct":14},"B","可能导致作业人员群死群伤",{"key":19,"text":20,"correct":14},"C","或者造成重大不良社会影响",{"key":22,"text":23,"correct":24},"D","会造成部分损失的",false,{"key":26,"text":27,"correct":24},"E","可能导致个别人员安全的","ABC","危险性较大的分部分项工程是指建设工程在施工过程中存在的、可能导致作业人员群死群伤或者造成重大不良社会影响的分部分项工程。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省B证（项目负责人）","建筑工程",0]