[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864417":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},864417,556,1,"单选题","冬季施工混凝土采用电热法进行（）时，应当注意防止发生触电。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","加热",false,{"key":16,"text":17,"correct":14},"B","测量",{"key":19,"text":20,"correct":21},"C","保温",true,{"key":23,"text":24,"correct":14},"D","防潮","冬季施工，混凝土采用电热法进行保温时应当注意防止发生触电，浇水养护时应当进行断电。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省B证（项目负责人）","建筑工程",0]