[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},864410,556,1,"单选题","临时用电组织设计及变更时，必须履行”编制、审核、批准”程序，由（）组织编制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工企业负责人",false,{"key":16,"text":17,"correct":14},"B","监理总工程师",{"key":19,"text":20,"correct":21},"C","电气工程技术人员",true,{"key":23,"text":24,"correct":14},"D","设计技术负责人","当临时用电组织设计及变更时，必须履行“编制、审核、批准”程序，由电气工程技术人员组织编制，经相关部门审核及具有法人资格企业的技术负责人批准后实施。变更用电组织设计时应补充有关图纸资料。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省B证（项目负责人）","建筑工程",0]